AUG 192016

Installation of Granite to the Water Feature

 

In the Water Plaza, the contractor is installing granite at the water feature. They are also installing materials in the planters. The contractor continues to install tile in the Water Plaza bathrooms.

In the Jetty, the contractor is installing precast pavers and benches. In addition, they are installing the handrail at the piers.

With ramp work nearly complete in Room 6, the contractor is switching their focus to the concrete cap at the river’s edge. They have begun installing brackets for the formwork and will continue that work through the end of the month. The contractor is also completing the gas line in Room 6 this week.

Work on the underbridges connecting the three blocks continues to progress. The cap pours are complete and the focus is shifting to construction of the underbridge structure and installation of precast pavers and guardrail.

Public Way Closures:

The westbound curb lane of Lower Wacker Drive between La Salle Street and Lake Street will have daily temporary closures between 7:00 AM and 5:30 PM.

The westbound curb lane of Lower Wacker Drive between La Salle Street and State Street may have daily temporary closures between 7:00 AM and 5:30 PM.

The westbound curb lane of Upper Wacker Drive between La Salle Street and State Street may have daily temporary closures between 9:30 AM and 3:30 PM.

For questions regarding Riverwalk operations and events contact the Department of Fleet and Facility Management.

For questions regarding the construction of the Riverwalk please Contact Us.

 

Chicago Riverwalk Work Zone Camera 1

 

Chicago Riverwalk Work Zone Camera 2