JUL 12016

Installation of Precast Pavers Next Week

 

In the Water Plaza, the contractor continues to install precast pavers and to work on the mechanical, electrical and plumbing for the bathrooms and vendor spaces in the Water Plaza. In addition, they continue to install the mechanical and electrical equipment for the water feature.

In the Jetty, the contractor is installing the pylons for the floating gardens. They also continue to work on installation of the fish habitats and to install proposed utilities for this bay and to work on the arcade spaces.

Backfilling operations continue in Room 6 along with utility installation. The contractor has finished framing the slab section for the ramp from upper Wacker Drive and will still rebar installation soon.

There will be no work on the Riverwalk from Saturday July 2, 2016 through Monday July 4 in observance of the 4th of July holiday.  

Public Way Closures:

The westbound curb lane of Lower Wacker Drive between La Salle Street and Lake Street will have daily temporary closures between 7:00 AM and 5:30 PM.

The westbound curb lane of Lower Wacker Drive between La Salle Street and State Street may have daily temporary closures between 7:00 AM and 5:30 PM.

The westbound curb lane of Upper Wacker Drive between La Salle Street and State Street may have daily temporary closures between 9:30 AM and 3:30 PM.

For questions regarding Riverwalk operations and events contact the Department of Fleet and Facility Management.

For questions regarding the construction of the Riverwalk please Contact Us.

 

Chicago Riverwalk Work Zone Camera 1

 

Chicago Riverwalk Work Zone Camera 2